13
Keston Heat - Frame & Header Kits
5 WALL MOUNTED INSTALLATION PROCEDURE
5.1 WALL MOUNTED SIDE BY SIDE OPTION
Ensure wall is capable of supporting the weight of boilers
to be mounted. Note. boiler weights can found in the
boiler Installation Instructions.
1. Cut the sides off the cardboard wall mounting
template/s (found in the boiler packaging) to create
the 50mm side clearance required.
2. Mark the height on to the wall from the oor to the top
of the boiler 1919mm.
4. Drill the required holes in the wall to t the wall mounting
plate plugs. (See boiler Installation Instructions for details)
5. Screw the wall mounting plate(s) to the wall.
5
Floor Mounting: Align centre line of template
to centre line of boiler and drill holes for
headers.
3. Tape the template/s to the wall ensuring the 50mm
side clearance per boiler requirement is adhered to.
3
4
2
1
continued . . . . .